Project Description

San Francisco Public Works hired Con-Quest Contractors, Inc., to complete sewer main replacement, water main replacement and pavement renovation work on Clayton Street, Clipper Street and Portola Drive.  The work under this contract also included, new ADA curb ramps, new sidewalk, curb and gutter work.  

Work Locations
     Clayton Street, from Ashbury Street to Market Street
​     Clipper Street, from Diamond Heights Boulevard to Dolores Street
     Portola Drive, from Woodside Avenue/O'Shaughnessy Boulevard to Corbett Avenue
     Twin Peaks Boulevard, from Portola Drive to Panorama Drive 

 


Pavement and Sewer Renovation
STATUS Completed
Location
Clayton Street, Clipper Street and Portola Drive
District
Start Date June 11, 2018
Completion Date March 31, 2020
Project Team

Con-Quest Contractors, Inc.
415-206-0524

 

Contact
Grace L.Moore, Public Affairs
Phone
(415) 558-5282