Project Description
San Francisco Public Works has hired Bauman Landscaping Construction Inc. to complete work on the Various Locations Pavement Renovation No. 58 and Sewer Replacement Project. The work scope will focus on infrastructure and safety enhancements across multiple locations in San Francisco. Our collaboration aims to reduce public inconvenience by efficiently coordinating our efforts whenever possible. The work to be completed under this contract includes curb ramp construction at 4-way and T-intersections, pedestrian and transit bulb-outs, sewer replacement/rehabilitation work, street base replacement work (concrete roadwork), pavement renovation, and traffic routing at various sites throughout the city. Construction will begin at the first location the week of February 19, 2024, and will be completed at the last location by September 2025.
Please note: The schedule may be subject to change due to rain, equipment breakdown or unforeseen field conditions. The planned work may cause traffic delays and necessitate temporary lane closures. Traffic control measures and flaggers will be implemented to minimize disruptions in the roadway. While construction is happening on your block, please allow extra travel time.
The blocks scheduled to be repaved or to have the concrete panels replaced are as follows:
· Cayuga Street (Valerton Ct. to Onondaga St.)
· Cayuga Street (Lyell St. to Milton St.)
· Onondaga Street (Rosella Ct. to Mission St.)
· University Street (Silver Ave. to Silliman St.)
· Sweeny Street (Cambridge St. to Princeton Ave.)
· Sweeny Street (University St. to Colby St.)
· Athens Street (France Ave. to Italy Ave.)
· Cambridge Street (Stoneybrook Ave. to Stoneyford Ave.)
· Cambridge Street (Bacon St. to Wayland St.)
· Oxford Street (Bacon St. to Wayland St.)
· Princeton Street (Bacon St. to Wayland St.)
· Harvard (Felton St. to Burrows St.)
· Howth Street (Mt. Vernon Ave. to Niagara Ave.)
· Louisburg Street (Mt. Vernon St. to Geneva Ave)
· Hamilton Street (Felton St. to Bacon St.)
· Bacon Street (Holyoke St. to Girard St.)
· Silliman Street (Girard St. to San Bruno St.) **
· Silliman Street (Harvard Street to Cambridge Street)
· Felton Street (Bowdoin St. to Hamilton St.)
· Avalon Street (LaGrande Ave. to Peru St.)
· 26th Street (Valencia St. to South Van Ness Ave.)
· Marston Ave (Edna St. to End)
· Staples Street (Detroit St. to Circular Ave.)
The blocks listed below are scheduled to include sewer main replacement or rehabilitation work.
· Harvard Street (Felton St. to Burrows St.)
· Silliman Street (Harvard St. to Oxford St.)
· 26th Street (Mission St. to Capp St.)
· Hamilton Street (Felton St. to Bacon St.)
· Bacon Street (Goettingen St. to Brussels St.)
· Sweeny Street (Cambridge St. to Princeton St.)
· Cambridge Street (Bacon St. to Wayland St.)
· Louisburg Street (Mt. Vernon St. to Niagara Ave.)
· Avalon Street (La Grande Ave. to Peru Ave.)
· Cayuga Avenue (Onondaga Ave to Valerton Ct.)
· Princeton Street (Wayland St. to Bacon St.)
· Detroit Street & Staples Avenue (Intersection)
· Bacon Street and Holyoke Street (Intersection)
The work hours may vary by location, however typical working hours are 7:30 a.m. to 5 p.m., Monday through Friday. Weekend work is allowed but has not been scheduled at this time.
San Francisco Public Works
San Francisco Public Utilities Commission
Bauman Landscape and Construction, Inc
(415) 447-4800 Office
(415) 447-4800 Ext. 9
After-Hours/Urgent