Construction Update November 2024

Segment 3 -Folsom Street 2nd St. to 5th St.

  • Excavate & Install Electrical conduits, pole foundations & pull boxes at Folsom St. 3rd St. intersection  11/11 through 11/22/24. 
  • Excavate & Install Electrical conduits, pole foundations & pull boxes at Folsom St. between 3rd St. & 4th St.  10/28-11/08/24   
  • Demo, excavate and install 24' VCP (sewer-pipe) on Folsom St., 4th St. to 3rd St. continues until 11/21/24

 

Segment 2 - Folsom Street 5th St. to 8th St.

  • Excavate,Shore & Install 15'' VCP sewer pipes on Rodgers St.     Pending
  • 7th Street to Harriet Street (Southside) catch-basin and culvert work 10/28/24 - 12/6/24 
  • Excavate & Install 24'' VCP On Folsom St between 7th st to 8th st (Starting at 7th St.) 11/14 through 12/31/24.

 

Segment 1 - Folsom Street 8th St. to 11th St.

  •  Electrical conduit, pole foundation & pull box installations  10/20/24- 11/22/24

 

For questions or coordination contact Dadisi Najib, SF Public Works

Project Description and Scope of Work:

SF Public Works has hired Mitchell Engineering to perform vital infrastructure improvements along Folsom Street between 2nd Street to 11th Street.  The Folsom Streetscape Project which began in May of 2024 has an overall duration of 2-years, 7-months (950-days) and is divided into three (3)-segments to help minimize impacts along the entire corridor. 

The project scope of work consists of sewer and water replacement, curb ramp reconstruction, pavement renovation landscaping, street lighting, and traffic signals.  

We are aware of the inconvenience caused by construction and apologize in advance. We will do everything possible to minimize the impact of our activities on your neighborhood. If you have concerns (scheduled deliveries, construction questions, accessibility needs, and access) please contact Public Affairs, Dadisi Najib. We will do everything possible to find a mutually agreeable solution.

Your cooperation will help this project be a success for your neighborhood and the City of San Francisco.  Thank you in advance for your understanding and cooperation.

For more information please visit:

https://www.sfmta.com/projects/folsom-howard-streetscape-project

https://www.sfmta.com/projects/folsom-street-implementation

 

 

 

 

Public Safety
Streetscapes
STATUS In Progress
Location
Folsom Street (2nd St. to 11th St.)
District
Start Spring, 2024
Completion Date October 31, 2026
Completion Fall, 2026
Release Date
Wednesday, January 31, 2024
Budget
45M
Client
SFMTA
Project Manager
Carol Huang
Project Team

Contractor - Mitchell Engineering

Contact
Ms. Dadisi Najib
Phone
628-271-2245
Download Project Files
Construction Notice