Innes Avenue Sidewalk Improvement Project

The Innes Avenue Sidewalk Improvement Project will improve pedestrian safety and accessibility along Innes Avenue, between Arelious Walker and Donahue Street. Improvements include construction of 6 ADA compliant curb ramps, 400 feet of new pedestrian safety rockslide catchment fence, and nearly 450 linear feet of new sidewalk, the majority of which is entirely missing. Design is expected to be complete by Winter 2023, and the project is anticipated to be open for use by Fall 2025.

Streetscapes
STATUS In Progress
Location
Innes Avenue from Arelious Walker to Donahue Street
District
Start Date July 30, 2024
Completion Date December 11, 2025
Release Date
Tuesday, March 21, 2023
Budget
$1.25 Million
Project Manager
Paul Barradas
Project Team

San Francisco Public Works

Contact
Paul Barradas
Phone
(628) 271-2580