Various Locations Pavement Renovation and Sewer Replacement No. 54

Project Updates - April 1, 2024 

South VanNess (Mission to Howard)

4/3/24-  Roadway paving (Southbound) in the slow and middle-lanes 

4/4/24-  Roadway paving (Northbound) slow and middle-lanes

4/5/24-  Roadway paving (north and southbound) fast lanes

 

San Francisco Public Works has contracted with Precision Engineering to install new sewer utilities and renovate the roadway at various locations in San Francisco as part of the Various Locations Pavement Renovation and Sewer Replacement No. 54 (VL54)  

Work locations include:
• 10th St: Market St to Division St
• 12th St: Howard St to Bernice St
• South Van Ness Ave: Mission St to Howard St
• South Van Ness Ave: Erie St to 17th St
• Bryant St: The Embarcadero to Beale St
• Leland Ave: Delta St to End
• Visitacion Ave: Loehr St to Hahn St
• Brussels St: Wilde Ave to Campbell Ave
• Campbell Ave: Brussels St to Goettingen St
• Wilde Ave: Brussels St to Alpha St/Goettingen St
• Velasco Ave: Schwerin St to Calgary St/Sawyer St

 

Work will consist of pavement renovation, curb ramp construction, sewer replacement, traffic control, and all related work. Sewer work will involve some street excavation to install new utilities and will be followed by pavement renovation (i.e. grinding and paving) activity once all utility work is complete. No interruption of sewer service is expected during construction. There may be a delay between utility work and final roadway renovation activity.

The typical sequence of sewer work is to install the new sewer main along the block(s) followed by sewer lateral replacement. Once the sewer main has been installed, Public Works’ engineering team will review video of the sewer laterals to determine which, if any, need to be replaced. The sewer laterals are the connection between the main and the sidewalk/curb. Crews will then schedule the sewer lateral replacement work. Sewer laterals are replaced on an as-needed basis depending on the condition of the line. Sewer service will not be interrupted during construction. Please continue to use your household plumbing as usual. 

During construction, traffic control will be implemented and "No Parking/Tow Away Zone" signs will be posted in active work areas. Local access for Residents, Deliveries and Emergency Services will be provided at all times during work hours. Please limit your use of the roadways within the construction work areas during working hours for the safety of the public and our employees, and to park in driveways or on adjacent blocks when No Parking Zones are posted. Should you need access to your property during work hours, please alert a crew member on site and note that there may be a slight delay to enter or exit your property to allow for crews to create a safe path of travel. Please follow instructions from crew members and follow all posted detour signs.

(*Please note:  Construction schedules, dates and durations are estimates subject to change due to rain, equipment breakdown, unforeseen field conditions, existing utility conflicts, crew availability, or early/delayed completion of work at a prior location.)

Pavement and Sewer Renovation
STATUS In Progress
Start Date October 10, 2022
Start Spring, 2022
Completion Summer, 2024
Release Date
Thursday, September 1, 2022
Budget
9.5 Million
Project Manager
Paul Barradas
Project Team

Contractor Contact: Precision Engineering

John Boylan, Project Manager

415-621-4882 after hours emergency 415-760-8744 (cell)

 

Contact
Dadis Najib, Public Affairs
Phone
628-271-2246