Various Locations Sewer Replacement and Pavement Renovation No. 41

San Francisco Public Works has contracted with Michael O’Shaughnessy Construction, Inc. to install new sewer utilities and renovate the roadway at various locations in District 10 as part of the Various Locations Sewer Replacement and Pavement Renovation No. 41 Project. Pavement Renovation and Sewer replacement work will occur between February 2020 and January 2021*.

Project locations:

  • Bass CT
  • Bell CT
  • Carpenter CT
  • Cashmere ST
  • Commer CT
  • Dukes CT
  • Galvez AVE
  • Garlington CT
  • George CT
  • Hawkins LN
  • Hillview CT
  • Innes AVE
  • La Salle AVE
  • Mabrey CT
  • Osceola LN
  • Progress ST
  • Reuel CT
  • Whitfield CT
  • Whitney Young CIR
  • Youngs CT

 

Work will consist of pavement renovation, sewer replacement, traffic control and all associated work. Sewer work will involve some street excavation to install new utilities and will be followed by pavement renovation (i.e. grinding and paving) activity once all utility work is complete. No interruption of sewer service is expected during construction. There may be a delay between utility work and final roadway renovation activity.

The typical sequence of sewer work is to install the new sewer main along the block(s) followed by sewer lateral replacement. Once the sewer main has been installed, Public Works’ engineering team will review video of the sewer laterals to determine which, if any, need to be replaced. The sewer laterals are the connection between the main and the sidewalk/curb. Crews will then schedule the sewer lateral replacement work. Sewer laterals are replaced on an as-needed basis depending on the condition of the line. Sewer service will not be interrupted during construction. Please continue to use your household plumbing as usual. 

During construction, traffic control will be implemented and "No Parking/Tow Away Zone" signs will be posted in active work areas. Local access for Residents, Deliveries and Emergency Services will be provided at all times during work hours. Please limit your use of the roadways within the construction work areas during working hours for the safety of the public and our employees, and to park in driveways or on adjacent blocks when No Parking Zones are posted. Should you need access to your property during work hours, please alert a crew member on site and note that there may be a slight delay to enter or exit your property to allow for crews to create a safe path of travel. Please follow instructions from crew members and follow all posted detour signs.

*Please note:  Construction scheduling and dates are subject to change due to rain, equipment breakdown, unforeseen field conditions, existing utility conflicts, crew availability, or early/delayed completion of work at a prior location.

Pavement and Sewer Renovation
STATUS Completed
District
Start Date February 01, 2019
Completion Date January 28, 2020
Budget
$3,800,000
Client
San Francisco Public Utilities Commission
Project Manager
Ramon Kong
Project Team

San Francisco Public Works

San Francisco Public Utilities Commission

Michael O'Shaughnessy Construction, Inc.
415-799-7043